menuMenu
Hazeldene House Care Suites

New Developments

Lower ground suites drylined and ready for skimming

Now in week 25 of the 34 week Phase 3 programme.

Structure:

  • Roof covering to be completed this week;
  • Scaffold will be dropped and rendering will commence shortly;

Internal:

  • Lower ground floor – Plastering work is nearing completion. The second fix work, decoration and vinyl floor coverings will also commence shortly;
  • Ground floor – Plastering work to be completed this week;
  • First floor – Plastering work has commenced and is ongoing;

Externals:

  • The external works are ongoing with the car parking, access roads, work to neighbouring properties and paving works to be carried out during the next 6 weeks.

Go Back

Enquire about Hazeldene House
Hazeldene House, Romford Road, Pembury, Nr Tunbridge Wells, Kent TN2 4AY
Copyright © Hazeldene House Limited | Website designed by StudioFord