menuMenu
Hazeldene House Care Suites

New Developments

Ground floor to first floor blockwork is progressing

Week 16 of the Phase 3 programme.

The first floor planks have been installed and the first floor to wall plate blockwork is proceeding.  The roof structure is to commence week commencing 1st April 2013.

The screeding to the lower ground floor and first fix activities were commenced this month.

Work is therefore on programme despite the weather related delays encountered to date.

Go Back

Enquire about Hazeldene House
Hazeldene House, Romford Road, Pembury, Nr Tunbridge Wells, Kent TN2 4AY
Copyright © Hazeldene House Limited | Website designed by StudioFord